性能验收试验
Inspection and performance acceptance test
检验和性能验收试验
4.5.13 The coal of boiler performance acceptance test shall be consistent with the designed coal, the allowable variation range for its industry analysis
4.5.13 锅炉性能验收试验使用的煤种应符合设计煤种,其工业分析的允许变化范围为:
1.3.1 The tasks of the site service personnel from BIDDER mainly include equipment delivery urgency, cargo open-box inspection, treatment of equipment quality problems, erection and commissioning, participating in test run and performance acceptance test.
4.7 All measurement points, primary element and local gauge for the performance acceptance test shall be supplied by BIDDER, shall conform to related specifications, codes and standards and shall be subject to confirmation
4.6.3 Other performance acceptance test shall be conducted as per related standards
4.6.3 其他性能验收试验采用相应标准执行。
1.1 This part is applied for the activities of supervision over manufacturing (QA/QC inspection) and performance acceptance test of the equipments (including subcontract outsourcing equipments) supplied by BIDDER in contract performance period, in order to guarantee the equipments meet the requirements regulated in stipulated in Appendix 1.
4.2 The place of performance acceptance test shall be specified in contract, and generally in the site of BUYER.
4.2 性能验收试验的地点由合同确定,一般为招标方现场。
4.1 The performance acceptance test is to check if all the performance of inspected contract equipment conforms to the requirements in Appendix 1. Test units specified by BUYER shall have relevant qualification.
1.2 BIDDER shall provide BUYER with standards concerning contract equipment supervision, inspection and performance acceptance test, in 3 months after the contract becoming effective. Relevant standards shall meet the regulations in Appendix 1.
4.4 BUYER will conduct the performance acceptance test, with presence of BIDDER. BUYER will propose the test outline and discuss with BIDDER for test is conducted at site, BIDDER shall coordinate as per requirements in Appendix 7; if test is conducted in factory, all labor and supplies for the test shall be offered by BIDDER.
3.2.4 Unit performance acceptance test shall be completed in half a year after 168 hours operation (half a year does not include the time for unit aging correction, which shall conform to the provisions of ASME PTC6-2004, and be as agreed upon by the BUYER).
1.15 Requirements of equipment supervision (inspection) and performance acceptance test specified in Technical Specification
1.15按技术规范书要求的设备监造(检验)和性能验收试验要求;
Performance acceptance test report shall be compiled by the testing units and admitted by both supply and demand parties.
性能验收试验报告由测试单位编写。报告结论供需双方均应承认。
Potentieel gevoelige of ongepaste informatie
Er worden alleen voorbeelden gegeven om u te helpen het woord of de woordcombinatie waarop u hebt gezocht, te vertalen. Deze worden niet door ons geselecteerd of gevalideerd en kunnen ongepaste taal bevatten. Wij vragen u melding te maken van voorbeelden die dienen te worden aangepast of verwijderd. Vertalingen met grof of informeel taalgebruik worden meestal rood of oranje gemarkeerd.