Example Sean is assigned to 20 hours of work for the Develop estimate task with a duration of 4 days.
Example Sean is scheduled to work 10 hours per day for the Develop estimate task.
例 松沢さんに、見積書作成 のタスクで 1 日 10 時間の作業時間が予定されているとします。
Example Sean is assigned to 20 hours of work for the Develop estimate task with a duration of 4 days. The scheduled work for the 4 days is 4, 4, 8, and 4 hours. You add the Cumulative Work field to the timephased portion of the Task Usage view. For the 4 days of this task's duration, the cumulative work values for Sean are 4, 8, 16, and 20.
Example Sean is scheduled to work 10 hours per day for the Develop estimate task. Based on the resource calendar, Sean's regular work capacity is eight hours per day. You add the Overallocation field to the timephased portion of the Resource Usage view. It shows that across the next five days, Sean is overallocated on this task by two hours per day.
In the Unique ID Successors field for the Develop estimate task, you see the entry 14FS+3d meaning that the task with Unique ID14 is a successor of this task, with a finish-to-start dependency, and a 3-day lag time.
ExampleYou want to review the successors of tasks in your project to analyze and refine the schedule. You add the Unique ID field and the Unique ID Successors field to the Task Sheet view. In the Unique ID Successors field for the Develop estimate task, you see the entry 14FS+3d meaning that the task with Unique ID14 is a successor of this task, with a finish-to-start dependency, and a 3-day lag time. Before the task with Unique ID14 can start, it must wait 3 days after the finish of this task. You also see that the Unique ID Successors field for the Conduct client meetings task is blank. You type 15FS to link this task to the task with unique ID15 with a finish-to-start dependency.
Er worden alleen voorbeelden gegeven om u te helpen het woord of de woordcombinatie waarop u hebt gezocht, te vertalen. Deze worden niet door ons geselecteerd of gevalideerd en kunnen ongepaste taal bevatten. Wij vragen u melding te maken van voorbeelden die dienen te worden aangepast of verwijderd. Vertalingen met grof of informeel taalgebruik worden meestal rood of oranje gemarkeerd.