By reviewing the timephased Actual Work Protected field for the task in the Task Usage view, you can see the number of hours he has worked on the assignment for the past two weeks.
ExampleSean is a drafter loaned to your project from another department. According to the value shown in Sean's Actual Work Protected field, he has worked 80 hours on your project over the past month. You're preparing the chargeback statement for the loaning department, and you use this value as the accurate number of hours worked by this resource.
By reviewing the Actual Overtime Work Protected field on the Resource Sheet view, you can review how much overtime each resource has reported so far for all assigned tasks.
By reviewing the Actual Overtime Work Protected field in the Resource Usage view, you can see that Sean has reported 2 hours, Chris has reported 4 hours, and Pat has reported 6 hours of overtime total for their assigned tasks.
ExampleSean has completed his assignment on the Develop electrical schematics task. By reviewing the timephased Actual Work Protected field for the task in the Task Usage view, you can see the number of hours he has worked on the assignment for the past two weeks. You're preparing an invoice to your customer which covers the last two weeks of work, and you use these values to itemize the charges.
Best UsesAdd the Actual Overtime Work Protected field to the timephased portion of the Task Usage view to review the uneditable timephased actual overtime work hours on tasks that have been submitted by team members. This field can be especially useful for seeing the breakdown of task overtime by time period, such as days, weeks, or months.
ExampleSean has completed his assignment on the Develop electrical schematics task. According to the value shown in the Actual Work Protected field for the assignment, he has reported 20 hours of work. You're preparing an invoice to your customer for this assignment, and you use this value as the accurate number of hours worked on this assignment.
Best Uses Add the Actual Overtime Work Protected field to any resource sheet view to review or filter the total uneditable actual overtime work hours for each resource.
As soon as a team member's actual work amounts are accepted by the project manager, those amounts are locked into the Actual Work Protected field and cannot be edited.
Er worden alleen voorbeelden gegeven om u te helpen het woord of de woordcombinatie waarop u hebt gezocht, te vertalen. Deze worden niet door ons geselecteerd of gevalideerd en kunnen ongepaste taal bevatten. Wij vragen u melding te maken van voorbeelden die dienen te worden aangepast of verwijderd. Vertalingen met grof of informeel taalgebruik worden meestal rood of oranje gemarkeerd.