The Main Contractor shall prepare and submit a comprehensive critical path programme immediately to the Engineer showing how he intends to design, procure, organise and carry out the works within the Time for Completion.
The Engineer reserves the right to examine, enquire and check the substantial feasibility of the Critical Path Programme and, if necessary, make suggestions and comments to it.
监理工程师有权检查、询问并核对关键路径项目的实质可行性,若有必要,提出建议和评论。
If and when it is found that the works are not keeping abreast with the Critical Path Programme, the Main Contractor must, with the utmost diligence, endeavour to catch up on time.
如果和当发现工作未跟上关键路径项目的进程,则总承包商须近最大的努力准时赶上进程。
In this respect, the Main Contractor is advised that it is his responsibility to up-date the Critical Path Programme at any time as and when appropriate and submit it to the Engineer for his reference.
为此,建议总承包商负责随时更新关键路径项目,并在合适时提交给监理工程师参考。
In the event of the Main Contractor becoming liable to pay damages to the Employer, the Critical Path Programme will be used by the Engineer as a basis for certifying the period of delay which has been caused by the Main Contractor.
The Nominated Sub-Contractors/ Suppliers and other Separate Contractors shall be allowed to examine the Programme and it is a particular requirement that all Separate Contractors shall signify in writing their acceptance to the details contained in the Critical Path Programme.
The Critical Path Programme is not intended to cover all building process but must indicate most of the dates of handover of areas from the Main Contractor to the Nominated Sub-Contactor or from the Nominated Sub-Contractor to the Main Contractor.
关键路径项目不包括所有构建过程,但须表明总承包商移交指定分包商或指定分包商移交总承包商的日期。
The Main Contractor shall co-ordinate all works with the Nominated Sub-Contractors/ Suppliers and other Separate Contractors in preparing the Critical Path Programme.
总承包商应与指定分包商/供应商以及其他独立承包商协调准备关键路径项目。
The dates concerning the relationships of the Separate Contractor programme to the Main Contractor's programme in this Critical Path Programme are subject to adjustment by agreement between the Main Contractor, Nominated Sub-Contractors/ Suppliers and Separate Contractors.
Les exemples vous aident à traduire le mot ou l’expression cherchés dans des contextes variés. Ils ne sont ni sélectionnés ni validés par nous et peuvent contenir des mots ou des idées inappropriés. Signalez des exemples à modifier ou à retirer. Les traductions potentiellement sensibles, inappropriées ou familières sont généralement marquées de rouge ou d’orange.