Each interim payment shall include such amounts for any claim as have been reasonably substantiated as due under the relevant provision of the Contract.
每次其中付款应包括已根据合同有关规定合理证明是有依据的、对任何索赔的应付款额。
This loss item is the second line item in each Interim Payment Certificate and relates to the reimbursement of costs which are subject to the payment of the contractor's fee.
这个损失项是每份临时支付证的第二排列项,涉及取决于承包人费用的支付的成本费的偿付。
Each interim payment shall include such amounts for any claim as have been reasonably substantiated as due under the relevant provision of the Contract. Unless and until the particulars supplied are sufficient to substantiate the whole of the claim, the Contractor shall only be entitled to payment for such part of the claim as he has been able to substantiate.
This loss item is the first line item in each Interim Payment Certificate and comprises a claim for costs to be reimbursed which are not subject to the payment of the contractor's fee (stipulated in article 8 of the terms of the Contract)
the amount certified in each Interim Payment Certificate within days after the Engineer receives the Statement and supporting documents; and
期中支付证书中开具的款额,时间是在工程师收到报表及证明文件之日起天内;以及
Deductions shall be made at the amortization rate of one-quarter(25%) of the amount of each Interim Payment Certificate (excluding the advance payment and deductions and repayments of retentions) issued during the Design-Build Period.
the Employer shall pay the amount certified in each Interim Payment Certificate within 56 days from the date on which the Employer's Representative received the Contractor's statement and supporting documents; and
(a)雇主应从雇主代表收到承包商的报表及证明文件之日起56天内,间承包商支付证书中开具的款额;
The Advance Payment Bank Guarantee shall contain a provision whereby, after each issue of an Interim Payment Certificate pursuant to Clause 15.6 [Issue of Interim Payment Certificates], its value shall be reduced pro rata by an amount equivalent to that amount of the Advance Payment recovered by the Employer under each Interim Payment Certificate in accordance with Clause 15.3.4 [Advance Payment], such reduction to be effected against presentation of a copy of the relevant Interim Payment Certificate to the guarantor under the Advance Payment Bank Guarantee.
During the Operation Service Period, a Maintenance Retention Fund shall be created by deducting five percent (5%) from the value of each interim payment, determined by the Employer's representative in accordance with Sub-Clause 14.7[Issue of Advance and Interim Payment Certificates], due to the Contractor, commencing with the first payment following the issue of the Commissioning Certificate, and continuing until the last Interim Payment Certificate is issued or until the amount in the Maintenance Retention Fund has reached the value(if any) stated in the Contract Data, whichever is earlier.
Les exemples vous aident à traduire le mot ou l’expression cherchés dans des contextes variés. Ils ne sont ni sélectionnés ni validés par nous et peuvent contenir des mots ou des idées inappropriés. Signalez des exemples à modifier ou à retirer. Les traductions potentiellement sensibles, inappropriées ou familières sont généralement marquées de rouge ou d’orange.